Steps :
1) Navigate to Site Map > Administration – Server Management > Jobs.
2) Click the New button in the Repeating Component Job Submission applet to create a new request.
3) In the Component/Job field, select the component job created earlier.
4 )Specify the Repeat Interval. In the Repeat Interval field, enter the number of units in the interval between repetitions of the component request. In the Repeat Unit field, click the drop-down list and select the type of unit in the interval between repetitions of the component request. One example of the type of unit is Days.
5) In the Repeat From field, select the instance from which the next repetition of the request should be executed.
6) To select the instance when the previous iteration of the request was:
7) Scheduled to start, select Scheduled Start.
8) Actually started, select Actual Start.
9) Ended, select End.
10) In the Repetitions field, specify the number of times that the component request will be repeated.
11) In the Expiration date field, select the date when the repeating component request will expire.
12) In the Delete Interval field, specify the number of units in the duration before the repeating component request will be deleted.
13) In the Repeat Unit field, select the type of unit in the duration before the repeating component request will be deleted (such as Days).
14) After specifying all the fields as required, save the record.
15) In the Component Request Parameters (Repeating Batch Job Parameter list applet), specify the parameter values as required.
16) Once complete, click the Submit button. (For Siebel 7.7 or higher, click the Start button. )
17) Navigate to the Repeating Component Requests Detail view to verify that the request has the Queued status.